WOW that was EXHILARATING!!!


A High Profile Client came to us with a Large (201 Units & 160,000 sf) and Very Complicated Project & 11 Weeks on the clock to meet the #421a deadline. .

We started the project on 4/6 had to circumvent

  • Mandatory Inclusionary Housing (HPD Filing)

  • Environmental issues (OER Filing Hazmat/Noise/ Air)

  • Flood Zone Compliance.

We put together a full DOB filing set in less than 10 Days (which is unheard of) !!!

The job was filed on 4/15 didn't get objections until 5/12 & we were still able to get Zoning Approval & Permit for #421a by the 6/15 deadline!!!

👏 INCREDIBLE Work by the full BILD Team!!! 👏